Bug #1064

closed

Epic #913: Phase 2

Epic #1053: Client Feedbacks

Bug #1057: Phase 3 bugs

Renew subscription

Added by Deeksha Singh about 1 month ago. Updated 24 days ago.

Status:
Closed
Priority:
Normal
Assignee:
Start date:
09/07/2026
Due date:
% Done:

0%

Estimated time:

Description

Start and expiry dates are displayed in inconsistent/incorrect formats, the subscription prorated amount is calculated incorrectly during negative testing, and the “Expires in” notification shows an incorrect remaining-days calculation.

Expected: Dates should use a consistent format and display the correct values, prorated subscription charges should be calculated accurately, and the expiry notification should show the correct remaining days.


Files

Actions #1

Updated by sumit thakur about 1 month ago

  • Status changed from New to Ready to QA
  • Assignee changed from sumit thakur to Deeksha Singh

Updated by Deeksha Singh 29 days ago

If we are updating the plan to 200 for 2 months then it should show 100/month instead of 200/month in the subscription/renew page under pich the best plan.
The updated plan should auto adjust according to the added plan


Actions #3

Updated by sumit thakur 25 days ago

  • Status changed from Reopen to Ready to QA
  • Assignee changed from sumit thakur to Deeksha Singh
Actions #4

Updated by Deeksha Singh 24 days ago

  • Status changed from Ready to QA to Closed
Actions